CAPM Practice: Demonstrate an understanding of project management planning
Matthias Calloway is planning a medical device installation project at Zenith Medical. He needs to determine resource requirements. The project will involve installing equipment at 15 hospital sites over 6 months, with each installation taking 3 days and requiring specialized technicians. Which factor is MOST important for Matthias to consider when determining the number of resources needed?