CAPM Practice: Demonstrate an understanding of project management planning

Declan Kwon is organizing planning documentation for a new vehicle design project at Drivechain Motors. Match each deliverable to the correct plan type. Items: 1. Quality metrics and acceptance criteria 2. Product specifications and technical requirements 3. Risk response strategies and contingency plans 4. Project milestones and schedule baseline Which option correctly matches each item to its description?

Key Concept

This question covers Demonstrate an understanding of project management planning under Demonstrate an understanding of project management planning (Project Management Fundamentals and Core Concepts).