CAPM Practice: Demonstrate an understanding of project management planning

Devi Kobayashi is planning a software implementation project at Kilowatt Power. She needs to determine how many developers, testers, and business analysts are required. Which planning component should she create to document the number and types of resources needed?

Key Concept

This question covers Demonstrate an understanding of project management planning under Demonstrate an understanding of project management planning (Project Management Fundamentals and Core Concepts).