CAPM Practice: Demonstrate an understanding of project roles and responsibilities
Nadia Iyer is managing a software upgrade project at Goldleaf Brands. A major scope change is proposed that requires additional funding. Who has the PRIMARY authority to approve this additional funding?
Key Concept
This question covers Demonstrate an understanding of project roles and responsibilities under Demonstrate an understanding of project roles and responsibilities (Project Management Fundamentals and Core Concepts).