CAPM Practice: Demonstrate an understanding of project roles and responsibilities

During a team meeting at Firefly Data, Rohan Brandt notices that two developers are having a heated disagreement about a technical approach. Rather than imposing a solution, Rohan asks questions to help the developers explore options and reach consensus. Which project manager role is Rohan demonstrating?

Key Concept

This question covers Demonstrate an understanding of project roles and responsibilities under Demonstrate an understanding of project roles and responsibilities (Project Management Fundamentals and Core Concepts).