CAPM Practice: Demonstrate an understanding of the various project life cycles and processes
Wanjiku Kobayashi is managing a temporary effort to implement a new customer portal at Firefly Data, with a defined start and end date. Her colleague manages the ongoing daily maintenance of existing systems. What distinguishes Wanjiku's work from her colleague's work?
Key Concept
This question covers Demonstrate an understanding of the various project life cycles and processes under Demonstrate an understanding of the various project life cycles and processes (Project Management Fundamentals and Core Concepts).