CAPM Practice: Demonstrate an understanding of the various project life cycles and processes
During planning, Elsa Bose at Everbloom Retail identifies that the project team will need access to the warehouse management system, but IT has not yet confirmed availability. How should Elsa categorize this situation?
Key Concept
This question covers Demonstrate an understanding of the various project life cycles and processes under Demonstrate an understanding of the various project life cycles and processes (Project Management Fundamentals and Core Concepts).