CAPM Practice: Demonstrate an understanding of the various project life cycles and processes

Zuri Menon is leading a software development project at Wavelength Biotech. During planning, the team identified that 'The vendor will deliver hardware by March 15' and 'Regulatory approval may be delayed due to increased scrutiny.' How should Zuri classify these two statements?