Ananya Korhonen's project at Echelon Tech has a risk response plan that specifies weekly risk reviews. During a busy week, a team member suggests skipping the review. How should Ananya respond?

Key Concept

This question covers Determine how to follow and execute planned strategies or frameworks under Determine how to follow and execute planned strategies or frameworks (Project Management Fundamentals and Core Concepts).