CAPM Practice: Determine how to follow and execute planned strategies or frameworks

During project initiation at Monolith Build Co, Riku Sabbagh is working with the sponsor to document expected business value. Which activity is Riku performing?

Key Concept

This question covers Determine how to follow and execute planned strategies or frameworks under Determine how to follow and execute planned strategies or frameworks (Project Management Fundamentals and Core Concepts).