CAPM Practice: Determine how to plan project iterations
A product owner wants to add a new user story to the sprint backlog one week into a 2-week sprint. What is the appropriate Scrum response?
Key Concept
This question covers Determine how to plan project iterations under Determine how to plan project iterations (Agile Frameworks/Methodologies).