CAPM Practice: Determine how to plan project iterations
An adaptive team's velocity over six sprints was: 32, 38, 29, 41, 35, 33. The product owner wants to know how many story points they can expect in the next sprint. What is the BEST forecasting approach?
Key Concept
This question covers Determine how to plan project iterations under Determine how to plan project iterations (Agile Frameworks/Methodologies).