Skip to content
PMPCAPM

Cost Performance Index (CPI)

Cost Performance Index (CPI) is an EVM efficiency metric that measures cost performance as the ratio of earned value to actual cost: CPI = EV / AC.

Explanation

The Cost Performance Index measures how efficiently the project is using its budget. A CPI of 1.0 means the project is exactly on budget. A CPI greater than 1.0 means the project is under budget (getting more value per dollar spent), and a CPI less than 1.0 means the project is over budget (getting less value per dollar spent).

The formula is CPI = EV / AC. For example, if EV = $40,000 and AC = $50,000, then CPI = 0.80, meaning the project is getting only 80 cents of value for every dollar spent.

CPI is considered the most critical EVM metric because research has shown that once a project reaches approximately 20% completion, CPI tends to remain relatively stable for the remainder of the project. This makes CPI a reliable predictor of final cost performance. CPI is also the most commonly used EAC forecasting factor.

Key Points

  • Formula: CPI = EV / AC
  • CPI > 1.0 = under budget; CPI < 1.0 = over budget
  • Most critical EVM metric; tends to stabilize after 20% completion
  • Primary input for EAC forecasting formulas

Exam Tip

CPI = EV / AC. Greater than 1.0 is good. CPI is the most important EVM metric and the most commonly tested. Once established, CPI rarely improves significantly.

Frequently Asked Questions

Related Topics

Test your knowledge

Practice scenario-based questions on this topic with detailed explanations.