Skip to content
PMPCAPM

Earned Value Management (EVM)

Earned Value Management (EVM) is a methodology that integrates scope, schedule, and cost data to assess project performance and progress objectively.

Explanation

Earned Value Management compares the amount of work that was planned with what was actually accomplished and the actual cost incurred. It requires three key data points: Planned Value (PV), Earned Value (EV), and Actual Cost (AC). From these three measurements, variances and performance indices are calculated.

EVM enables the project manager to answer critical questions: Are we ahead of or behind schedule? Are we over or under budget? How much will the project cost at completion? By comparing EV to PV, schedule performance is measured. By comparing EV to AC, cost performance is measured.

Key EVM metrics include Schedule Variance (SV = EV - PV), Cost Variance (CV = EV - AC), Schedule Performance Index (SPI = EV / PV), Cost Performance Index (CPI = EV / AC), Estimate at Completion (EAC), Estimate to Complete (ETC), Variance at Completion (VAC), and To-Complete Performance Index (TCPI). EVM provides early warning signals of performance problems and supports data-driven decision making.

Key Points

  • Integrates scope, schedule, and cost measurement
  • Three foundational values: PV, EV, and AC
  • Calculates variances (SV, CV) and indices (SPI, CPI)
  • Enables forecasting of final project cost and schedule

Exam Tip

EVM is heavily tested on both PMP and CAPM exams. Memorize all formulas and know how to interpret positive/negative variances and indices above/below 1.0.

Frequently Asked Questions

Related Topics

Test your knowledge

Practice scenario-based questions on this topic with detailed explanations.